Structural Demolition RAMS

DemolitionStructural demolitionUKCDM 2015Draft v1
1

Scope of works

This RAMS covers structural demolition carried out by demolition operatives on a UK construction or maintenance site. It sets out the method, the principal hazards and the control measures to be applied. Site-specific details (address, client, access, dates and supervisor) are completed for each job before the document is issued for principal-contractor review.

2

Sequence of works

  1. 1Review structural and asbestos surveys; agree the sequence
  2. 2Isolate services and set up exclusion zones
  3. 3Soft strip, then demolish in the planned controlled sequence
  4. 4Suppress dust and manage waste segregation
  5. 5Inspect the area and confirm stability throughout
3

Hazards, risk rating & controls

Risk = likelihood × severity (1–25). Initial is before controls; residual is with controls applied.

Premature / uncontrolled structural collapse

Initial20Residual5

Who’s at risk: Operatives, Public, Other trades

  • Demolition sequence designed by a competent person; structural survey reviewed
  • Exclusion zones and monitoring during the works
  • Top-down, controlled sequence; no undermining of supporting elements

Disturbance of asbestos-containing materials (ACMs)

Initial15Residual5

Who’s at risk: Operatives, Other trades

  • Refurbishment & demolition asbestos survey reviewed before work
  • Stop work and report if suspected ACMs are found
  • Licensed contractor engaged for licensable asbestos work

Manual handling of materials and equipment

Initial9Residual3

Who’s at risk: Operatives

  • Mechanical handling/aids used where reasonably practicable
  • Loads assessed; team lifts for awkward or heavy items
  • Operatives briefed on safe lifting technique

Slips, trips and falls on the level

Initial6Residual2

Who’s at risk: Operatives, Other trades

  • Work area kept clear; good housekeeping enforced
  • Cables and hoses routed away from walkways
  • Spillages cleaned immediately; adequate lighting maintained
4

PPE

  • Hard hat
  • Safety boots
  • Hi-vis
  • Gloves
  • RPE and eye protection for dust
5

Competence

  • Competent demolition supervisor (e.g. CCDO)
  • Asbestos awareness (UKATA/IATP)
  • Plant operator certification

Schemes (CSCS, PASMA, IPAF…) evidence competence; they are not statutory requirements in themselves.

6

Permits & legislation

Permit to workAsbestos notification where licensable
CDM 2015Control of Asbestos Regulations 2012BS 6187 (demolition)COSHH 2002
This is a draft, not a finished RAMS. The content above is a starting point generated from recognised hazards and controls for this task. A competent person must review it and confirm it is suitable and sufficient for the specific site before use. It is not legal advice or a guarantee of acceptance.